PROGRESS REPORT OF UPPER KRISHNA PROJECT AS AT 30.06.2010
( In accordance with the Listing Agreement entered into with the National Stock Exchange)
UNITS / PROGRAMMED
PROGRESS AS AT 30.06.2010

A. NARAYANPUR DAM AND ALLIED WORKS

B. ALMATTI DAM AND ALLIED - WORKS

i) Left Bank Earth and Masonry Dam-
EL 528.800 m
ii) Spill Way - EL 509.016 m
iii) Right Bank Masonry Dam-Power Dam -
EL 528.760 m
iv) Non-overflow Section -EL.528.760m
Providing Gates - 26 Nos.

Completed.


Completed.

 

The works pertaining to Dam including Gates have been completed. Water is stored up to FRL519.60 m and being utilized.

C. NARAYANPUR LEFT BANK CANAL

i) Main Canal - Length - KM 78


Irrigation Area - 47,233 ha.




Completed.
The canal is providing irrigation to Shorapur Taluk of Gulbarga District.

53,590 hectares

ii) Shahpur Branch Canal -

Main Canal - Length - KM 76

Irrigation Area - 1,22,120 ha.

Completed. The canal is providing irrigation to Shorapur & Shahapur Taluk of Gulbarga District.

1,11,005 hectares
iii) Mudbal Branch Canal -

Main Canal - Length - KM 50.80


Irrigation Area - 51,000 ha.
Completed. The canal is providing irrigation to Shahapur & Jewargi Taluk of Gulbarga District.

45,015 hectares

iv) Indi Branch Canal -

Main Canal - Length - KM 175

Irrigation Area - 1,31,260 ha.

Works are Completed. The canal is providing irrigation to Surpur & Jewargi Taluks of Gulbarga District and Sindagi & Indi Taluks of Bijapur District.

1,31,295 hectares

v) Jewargi Branch Canal -

Main Canal - Length - KM 86.36






Irrigation Area - 57,100 ha

The canal contemplates to provide irrigation to Shahapur & Jewargi Taluks of Gulbarga District. The work on entire main canal upto Km. 86.36 and 168 CD works are completed. Distributary No.1 to 18 are fully completed. Water has been let out in all the Distributaries.

58,121 hectare

D. NARAYANPUR RIGHT BANK CANAL -
Main Canal - Length - KM 95.00











Irrigation Area - 84,000 ha.

The NRBC canal contemplates irrigation to Lingasugur & Deodurga Taluks of Raichur District. The entire length of 95 Kms of main canal including 195 CD works are completed. All the Distributaries No.1 to 18 are completed. Certain balance works of Branch Distributary, Laterals on Distributary No.15, 16 & 18 are in progress. Water is let out in main canal & Distributary 1 to 18.

84,000 hectare.

E. ALMATTI LEFT BANK CANAL -
Main canal - Length - KM 93.115














Irrigation Area - 20,235 ha.


ALBC LI scheme contemplates irrigation to Muddebihal & Basavana Bagewadi Taluks of Bijapur District. The headwork is completed. Main Canal works from Km. 0.00 to 67.00 completed. Works from Km. 67.00 to 85.00 except Km.72 are almost completed. Among 43 Distributaries, Distributary No. 1 to 28 are completed and Distributary 29 to 40, the works are also almost completed except Distributary No.29.

21,998 hectare

F. ALMATTI RIGHT BANK CANAL -
Main canal - Length - KM 67.50









Irrigation Area - 9,900 ha.

ARBC LI scheme contemplates irrigation to Hungund & Bagalkot Taluks of Bagalkot District. The headwork and jackwell structure are completed. The entire length of main canal from Km. 0.00 to 67.00 completed. Distributaries 1 to 24 completed. Water is let out in main canal & Distributary No.1 to 24.

9,222 hectare.

G. MULWAD LIFT IRRIGATION SCHEME -
Main Canal - Length - KM 107.40
















Irrigation Area - 30,850 ha.

Mulwad LI scheme contemplates irrigation to Basavana Bagewadi Taluk of Bijapur District & Jamakhandi Taluk of Bagalkot District. Headworks and lead off canal completed. The entire length of East canal upto 17.40 Kms. completed. Distributaries, No. 1 to 6 are completed. Tender invited for extension of Distributary No.6

West Canal from Km.0.00 to 78.00 is completed. 1 to 43 Distributaries are completed. Water is let out under East Canal, West Canal and Distributaries thereunder.

21,897 hectare.

H. RAMPUR LIFT IRRIGATION SCHEME-
Main canal - Length - KM 37.50

 

 

 








Irrigation Area - 20,235 ha.

The Rampur LI Scheme contemplates irrigation to Lingasugur Taluk of Raichur District. First head work at Navali and second head work near Anahosur completed. 14 Km. length of lead off channel is completed. The entire length of East Branch Canal from Km. 0 to 20 and West Distributary from Km. 0 to 26.14 are completed. The distributary network including laterals & Field Irrigation Canals under lead off channel, East Branch Canal and West distributary are completed & water let out for irrigation.

19,406 hectare

I. INDI LIFT IRRIGATION SCHEME -
Main Canal - Length - KM 97.30













Irrigation Area - 41,900 ha.

The Indi LI scheme contemplates irrigation to Shorapur Taluk of Gulbarga District & Sindagi Taluk of Bijapur District. The construction of Head work including pumping machinery completed & commissioned. Entire main canal work from Km 0.00 to 97.30 completed. Distributary No.1 to 40 are completed except Distributary No.22. Balance works on Distributary No.22 is in progress. Water has been let out under completed Distributary network.

41,900 hectare

2. OTHER PROJECTS UNDER KRISHNA BASIN

A. Ramthal (Marol) Lift Irrigation Scheme

 

This LI Scheme contemplates providing of irrigation facilities to Hungund Taluk of Bagalkot district for 26,200 hectare by utilising 5.84 TMC of water. The location of the first jackwell is on the backwater of Narayanapur reservoir, near Marol village. The work for construction of intake channel, jackwell, pumping machinery, raising main, delivery chamber, etc. for first Head Work awarded on turnkey basis completed. Km. 0 to 8 of 1st Stage West Main Canal work is nearing completion. Further earth work of 1st stage West Main Canal Km.8.00 to 21.00 is under progress. Work on Distry. No.1 to 6 ( except Dy.No.4) are in progress. Tender invited for Distry. No.4. The Second head work awarded on turn key basis, is in advance stage of progress. The work of 110 KV transmission line is completed.
B. Teggi-Siddapur Lift Irrigation Scheme This LI scheme envisages utilization of 1.20 TMC of water (0.90 TMC under scheme 'A') from the backwater of Almatti reservoir to provide irrigation to 3,000 hectare of Bilagi taluk of Bagalkot district. Tender for electromechanical works including balance work of Jackwell on turn key basis was approved by KBJNL Board subject to certain conditions. Works of Main Canal from Km.0.00 to 12.18 in two packages are under progress.
C.Thimmapur Lift Irrigation Scheme
(ARBC Stage-II)
This LI scheme takes off from Km.4.92 of ARBC. The scheme contemplates providing irrigation to 20,100 hectare in Hungund taluk of Bagalkot district. The work of construction of intake channel, jackwell, pumping machinery, raising main, delivery chamber etc. awarded on turnkey basis is almost completed. Works of Main Canal Km.0.00 to 10.00 from Delivery Chamber-1 awarded in two packages are under progress. The tender for main canal from Km.0.00 to 5.00 of DC-2 invited and is in process. Terminal bay work for power supply to Head Work is in progress.
D. Sonna LI Schemes This LI schemes envisage utilization of total 0.233 TMC of water from the backwater of Almatti reservoir to provide irrigation to 1,055 hectare lands of Bilagi taluk. The construction of jackwell, intake channel provide pumping machinery etc., awarded on turnkey basis completed. Package work of entire canal network is nearing completion.

E. Rolli - Mannikeri LI Schemes
This LI scheme envisage utilization of total 0.73 TMC of water in the backwater of Almatti reservoir to provide irrigation to 2,350 hectare lands of Bilagi Taluk. Tender for construction of jackwell work, providing pumping machinery etc., on turn key basis is approved in KBJNL Board meeting subject to certain conditions.
3. BARRAGES ON RIVER BHIMA.
A. Ghattarga Barrage Work completed
B. Kallur 'B' Barrage Work completed.
C. Sonthi Barrage - Lift Irrigation Scheme Government has accorded administrative approval to the modified Sonthi Barrage/ LI Scheme at a cost of Rs.188.00 crores. The scheme contemplates providing irrigation for 16,000 ha by utilizing 4 TMC of water. Civil work of barrage as per original scope and the modified scope completed. Erection of all 37 vertical gates completed. For lifting system, the excavation for Delivery Chamber and jackwell cum pump house completed. RCC raft foundation for jackwell is in progress. M.S.Pipe rising main is laid for about 3.40 Km. Out of 3000 Mtr length of intake canal, excavation for 1250 mtr length is completed. Sump model studies for pumping machineries conducted. Construction of Feeder Canal Km. 0.00 to 1.75 commenced. Power Transmission Line work for Head work awarded recently.
D. Yadgir Barrage

Work completed.

E. Joladagi - Gudur Barrage Work completed.

4. BARRAGE ON RIVER KRISHNA


Gugal Barrage

The barrage work is taken up across river Krishna near Gugal village of Deodurga Taluk. Civil work of Bridge-cum-Barrage is completed. In the work of providing 69 vertical gates, fabrication of 67 gates completed. Erection of 43 sets of embedded parts are completed.

5. BARRAGE ON RIVER MANJRA

A. Jirgihal Barrage

B. Manikeshwar Barrage

C. Halhalli Barrage

D. Chandapur Barrage

It is envisaged to utilize 4.80 TMC of water by constructing 4 barrages across river Manjra of Godavari basin in Bidar district. Excavation for foundation completed. Laying of rafts and concreting of Piers in progress. Fabrication & erection of embedded parts for all four barrages are in progress. Chandapur Barrage work is in advance stage of completion.

Details on the Investors Grievances received/redressed and pending for redressal at the period ending 30.06.2010 (details as submitted by the R&TAs & in the Company)

Pending as at 31.03.2010

Received during the quarter between 01.04.2010 & 30.06.2010
Total
Disposed off during the said period
Pending at the end of 30.06.2010
Nil
388
388
379
11

Note:
1) In general, the progress of work in the project is satisfactory.
2) Investors' grievances are being attended by the R&TAs appointed by the Company and in the in-house of the Company .
3) Investors who have not yet surrendered bond certificates in respect of Series II (DDB), VIIB, VIIIB, VIIIC, IXA, XA, XB, XC, XD, XIB, XIC, XID & XIIA may surrender their Bond certificates at the earliest to claim refund.

 

Date : 26.07.2010

Place: Bangalore..

...

BASAVARAJU

MANAGING DIRECTOR

 

 

 

 