PROGRESS REPORT OF UPPER KRISHNA PROJECT AS AT 31.12.2011
( In accordance with the Listing Agreement entered into with the National Stock Exchange)
UNITS/PROGRAMMED
PROGRESS AS AT 31.12.2011
A. NARAYANPUR DAM AND ALLIED WORKS

COMPLETED
B. ALMATTI DAM AND ALLIED - WORKS
i) Left Bank Earth and Masonry Dam- EL 528.800 m
ii) Spill Way - EL 509.016 m
iii) Right Bank Masonry Dam-Power Dam - EL 528.760 m
iv) Non-overflow Section -EL.528.760m
Providing Gates - 26 Nos.



Completed.

The works pertaining to Dam including Gates have been completed. Water is stored upto FRL.519.60 m and being utilised.

C. NARAYANPUR LEFT BANK CANAL
i) Main Canal -
Length - KM 78
Irrigation Area - 47,233 ha.

ii) Shahpur Branch Canal -
Main Canal - Length - KM 76
Irrigation Area - 1,22,120 ha.

iii) Mudbal Branch Canal -
Main Canal - Length - KM 50.80
Irrigation Area - 51,000 ha.


iv) Indi Branch Canal -
Main Canal - Length - KM 175
Irrigation Area - 1,31,260 ha.




v) Jewargi Branch Canal -
Main Canal - Length - KM 86.36
Irrigation Area - 57,100 ha


Completed. The canal is providing irrigation to Shorapur Taluk of Gulbarga District.
53,590 hectares

Completed. The canal is providing irrigation to Shorapur & Shahapur Taluk of Gulbarga District.
1,11,005 hectares

Completed. The canal is providing irrigation to Shahapur & Jewargi Taluk of Gulbarga District.
45,015 hectares

Works are Completed. The canal is providing irrigation to Surpur & Jewargi Taluks of Gulbarga District and Sindagi & Indi Taluks of Bijapur District.
1,31,295 hectares

The canal contemplates to provide irrigation to Shorapur & Jewargi Taluks of Gulbarga District. The work on entire main canal upto Km. 86.36 and 168 CD works are completed. Distributary No.1 to 18 are fully completed. Water has been let out in all the Distributaries.
58,778 hectare

D. NARAYANPUR RIGHT BANK CANAL -
Main Canal - Length - KM 95.00
Irrigation Area - 84,000 ha.

The NRBC canal contemplates irrigation to Lingasugur & Deodurga Taluks of Raichur District. The entire length of 95 Kms of main canal including 195 CD works are completed. All the Distributaries No.1 to 18 are completed. Certain balance works of Laterals on Distributary No.15, 16 & 18 are in progress. Water is let out in Main Canal & Distributary 1 to 18.

84,000 hectare.

E. ALMATTI LEFT BANK CANAL -
Main canal - Length - KM 93.115
Irrigation Area - 20,235 ha.

ALBC LI scheme contemplates irrigation to Muddebihal & Basavana Bagewadi Taluks of Bijapur District. The headwork is completed. Main Canal works from Km. 0.00 to 67.00 completed. Works from Km. 67.00 to 85.00 except Km.72 are almost completed. Balance works of Km.72 taken up separately commenced recently. Distributary No. 1 to 40 are completed. Water let out for irrigation upto Km.66.00 and Distry.No.1 to 27.

23,480 hectare.

F. ALMATTI RIGHT BANK CANAL -
Main canal - Length - KM 67.50
Irrigation Area - 9,900 ha.

ARBC LI scheme contemplates irrigation to Hungund & Bagalkot Taluks of Bagalkot District. The headwork and jackwell structure are completed. The entire length of main canal from Km. 0.00 to 67.00 completed. Distributaries 1 to 24 completed. Water is let out in main canal & Distributary No.1 to 24.

9,222 hectare.

G. MULWAD LIFT IRRIGATION SCHEME
Main Canal - Length - KM 107.40
Irrigation Area - 30,850 ha.

Mulwad LI scheme contemplates irrigation to Basavana Bagewadi Taluk of Bijapur District & Jamakhandi Taluk of Bagalkot District. Headworks and lead off canal completed. The entire length of East canal upto 17.40 Kms. completed. Distributaries, No. 1 to 6 are completed. Extension of Distributary No.6 work is nearing completion.

West Canal from Km.0.00 to 78.00 is completed. 1 to 43 Distributaries are completed. Water is let out under East Canal, West Canal and Distributaries thereunder.

22,797 hectare.

H.RAMPUR LIFT IRRIGATION SCHEME-
Main canal - Length - KM 37.50
Irrigation Area - 20,235 ha.

The Rampur LI Scheme contemplates irrigation to Lingasugur Taluk of Raichur District. First head work at Navali and second head work near Anahosur completed. 14 Km. length of lead off channel is completed. The entire length of East Branch Canal from Km. 0 to 20 and West Distributary from Km. 0 to 26.14 are completed. The distributary network including laterals & Field Irrigation Canals under lead off channel, East Branch Canal and West distributary are completed & water let out for irrigation.

19,406 hectare

I. INDI LIFT IRRIGATION SCHEME -
Main Canal - Length - KM 97.30
Irrigation Area - 41,900 ha.

The Indi LI scheme contemplates irrigation to Shorapur Taluk of Gulbarga District & Sindagi Taluk of Bijapur District. The Head work and entire main canal work from Km 0.00 to 97.30 completed including Distributary No.1 to 40 except Distributary No.22. Water has been let out under completed Distributary network.

41,900 hectare

2. OTHER PROJECTS UNDER KRISHNA BASIN
A. Ramthal (Marol) Lift Irrigation Scheme This LI Scheme contemplates providing of irrigation facilities to Hungund Taluk of Bagalkot district for 26,200 hectare by utilising 5.84 TMC of water. First Headwork on the backwater of Narayanapur reservoir, near Marol taken up on turn key basis is completed. Km. 0 to 8 and Km.15.00 to 21.00 of 1st Stage West Main Canal completed. Further 1st stage West Main Canal Km.8.00 to 15.00 is nearing completion. Tenders awarded recently for 1st stage West Main Canal Km.21.00 to 45.00 and for Dy.No.12.00 to 18.00. Work on Distry. No.1 to 6 (except Dy.No.4) are completed. Distry. No.4 and Dy.No.7 to 11 are in progress. The work of East canal Km.0.00 to 6.00 is under progress. The Second head work near Ramwadgi awarded on turn key basis is almost completed. Work of 110 KV transmission line is completed. The estimates of canal net work of 2nd stage are under preparation.
B. Teggi-Siddapur Lift Irrigation Scheme This LI scheme envisages utilization of 1.20 TMC of water (0.90 TMC under scheme 'A') from the backwater of Almatti reservoir to provide irrigation to 3,000 hectare of Bilagi taluk of Bagalkot district. Head work with electromechanical works including balance work of Jackwell awarded on turn key basis is in progress. Works of Main Canal from Km.0.00 to 12.18 awarded in two packages, are also almost completed.
C. Thimmapur Lift Irrigation Scheme
(ARBC Stage-II)*
This LI scheme takes off from Km.4.92 of ARBC. The scheme contemplates providing irrigation to 20,100 hectare in Hungund taluk of Bagalkot district. The work of construction of intake channel, jackwell, pumping machinery, raising main, delivery chamber etc. awarded on turnkey basis is almost completed. Works of Main Canal Km.0.00 to 10.00 from Delivery Chamber-1 awarded in two packages nearing completion. Main Canal from Km.0.00 to 5.00 of DC-2 is in progress. Terminal bay work for power supply to Head work is completed.
D. Sonna LI Schemes This LI schemes envisage utilization of total 0.233 TMC of water from the backwater of Almatti reservoir to provide irrigation to 1,055 hectare lands of Bilagi taluk. The Scheme is completed & comissioned. Water is let out in the canal network for irrigation.
E. Rolli-Mannikeri LI Schemes This LI scheme envisage utilization of total 0.73 TMC of water in the backwater of Almatti reservoir to provide irrigation to 2,350 hectare lands of Bilagi Taluk. Construction of jackwell work, providing pumping machinery etc., awarded on turn key basis is in progress. Works of canal network awarded recently.
3. BARRAGES ON RIVER BHIMA
A. Ghattarga Barrage
B. Kallur 'B' Barrage

Work completed
Work completed
C. Sonthi Barrage - Lift Irrigation Scheme The scheme contemplates providing irrigation for 16,000 ha by utilizing 4 TMC of water. Civil work of barrage as per original scope and the modified scope completed. Erection of all 37 vertical gates completed. For lifting system, the excavation for Delivery Chamber and jackwell cum pump house completed. RCC raft foundation for jackwell completed. M.S.Pipe rising main is laid for about 3.40 Km. Out of 3000 Mtr length of intake canal, excavation for 1250 mtr length is tackled. Pumping machineries brought to site. Construction of Feeder Canal Km. 0.00 to 1.75 is in progress. Power Transmission Line work is in progress.

D. Yadgir Barrage

E. Joladagi - Gudur Barrage

Work completed.

Work completed.
4. BARRAGE ON RIVER KRISHNA
Gugal Barrage
The barrage work is taken up across river Krishna near Gugal village of Deodurga Taluk. Civil work of Bridge-cum-Barrage is completed. The work of providing 69 vertical gates is also almost completed.

5. BARRAGE ON RIVER MANJRA

A. Jirgihal Barrage

B. Manikeshwar Barrage

C. Halhalli Barrage

D. Chandapur Barrage

It is envisaged to utilize 4.80 TMC of water by constructing 4 barrages across river Manjra of Godavari basin in Bidar district. Chandapur Barrage work is completed. Construction of Jirigihal & Manikeshwar Barrages are in advance stage of progress. Further Laying of rafts, concreting of Piers, laying of Deck Slab and Fabrication & erection of embedded parts / gates for Halhalli Barrages is in progress.
Details on the Investors Grievances received/redressed and pending for redressal at the period ending 31.12..2011 (details as submitted by the R&TA & in the Company service provider)
Pending as at 30.09.2011 Received during the quarter between 01.10.2011 & 31.12.2011 Total Disposed off during the said period Pending at the end of 31.12.2011
Nil
386
386
386
Nil
Note:
1) In general, the progress of work in the project is satisfactory.
2) Investors' grievances are being attended by the R&TA service provider M/s. RMV Solutions, 409, 'Joe Nivas', Chickamaranahalli, New BEL Road, Mathikere, Bangalore-560 054 (Telephone No.080-23600662, Cell Nos. 09343779958) appointed by the Company and in the in-house of the Company.
3) Investors who have not yet surrendered bond certificates in respect of Series II (DDB), VIIIA, VIIIB, VIIIC, IXA, XA, XB, XC, XD, XIB, XIC, XID & XIIA may surrender their Bond certificates at the earliest to claim refund.
TO WHOMSOEVER IT MAY CONCERN

 

To the Series II Deep Discount Bondholders of Krishna Bhagya Jala Nigam Ltd., Bangalore

Sub: Refund of matured Deep Discount Bond amount

********

As per the record / data bank maintained by the R&TA-service provider, M/s. RMV Solutions, Bangalore, there are about 6400 DDB folios / bondholders have not claimed their matured bond amount. The Series II Deep Discount Bonds of our Nigam issued during 1996 was due for payment on maturity on 17.06.2006 ( on completion of 10 years ). As per the terms of the issue, redemption of bond amount can be made only against surrender of the original Letter of Allotment (LOA) or the original Bond Certificate (BC). Almost all the Allottees / Bondholders have surrendered their original LOAs / BCs and taken the refund of the bond amount. Now, as per the information provided by the R&TA service provider, there are about 6400 bondholders yet to surrender their original LOA / BC ( out of 167657 original Allottees / Bondholders ). We have been publishing the status of redemption and requesting the unclaimed bondholders to surrender their original LOA / BC for redemption purpose, right from the date of maturity, i.e., 17.06.2006 upto this date. We have also posted this information on our website www.kbjnl.com. But we find, still there are about 6400 deep discount bondholders yet to respond in surrendering the original LOA / BC for redemption purpose.

As per the Company Law provisions [ Section 205(C) ], the unclaimed bond amount will have to be deposited in Central Govt. account called " Investor Education Protection Fund" (IEPF) account on completion of 7 years from the date of payment on maturity, 17.06.2006. Accordingly our Company is required to deposit the unclaimed and left over bond amount by 16.06.2013 in IEPF account. Once the amount is deposited in IEPF Account, it will go to Central Govt. and nobody can claim for refund of bond amount and it will be a loss to the bondholders. Hence the concerned unclaimed Deep Discount Bondholders may please surrender their original Letter of Allotment / Bond Certificate at the earliest to our Company or to the R&TA service lending agency, M/s. RMV Solutions, 409, 'Joe Nivas', Chickamaranahalli, New BEL Road, Mathikere, Bangalore-560 054 ( Telephone No.080-23600662, Cell Nos. 09343779958 of Mr. Ramesh Manuel and 0991653475 of Ms.Yeshaswini) at the earliest for refund of the matured bond amount. If there is any grievance, like change of address, Transmission of bonds, issue of duplicate LOA/BC etc., the same may also be addressed for immediate redressal and take it for redemption.

For kind information and for urgent needful action at your end.


Date : 27.01.2012....................................................
Place : Bangalore.. ....................................... MANAGING DIRECTOR

 

 

 

 