PROGRESS REPORT OF UPPER KRISHNA
PROJECT AS AT 31.12.2011
( In accordance with the Listing Agreement
entered into with the National Stock Exchange)
|
|
UNITS/PROGRAMMED
|
PROGRESS AS AT 31.12.2011
|
| A. NARAYANPUR
DAM AND ALLIED WORKS |
COMPLETED
|
B. ALMATTI
DAM AND ALLIED - WORKS
i) Left Bank Earth and Masonry Dam- EL 528.800
m
ii) Spill Way - EL 509.016 m
iii) Right Bank Masonry Dam-Power Dam - EL 528.760
m
iv) Non-overflow Section -EL.528.760m
Providing Gates - 26 Nos. |
Completed.
The works pertaining to Dam including Gates have
been completed. Water is stored upto FRL.519.60 m
and being utilised.
|
|
C. NARAYANPUR LEFT BANK CANAL
i) Main Canal -
Length - KM 78
Irrigation Area - 47,233 ha.
ii) Shahpur Branch Canal -
Main Canal - Length - KM 76
Irrigation Area - 1,22,120 ha.
iii) Mudbal Branch Canal -
Main Canal - Length - KM 50.80
Irrigation Area - 51,000 ha.
iv) Indi Branch Canal -
Main Canal - Length - KM 175
Irrigation Area - 1,31,260 ha.
v) Jewargi Branch Canal -
Main Canal - Length - KM 86.36
Irrigation Area - 57,100 ha
|
Completed. The canal is providing irrigation to Shorapur
Taluk of Gulbarga District.
53,590 hectares
Completed. The canal is providing irrigation to Shorapur
& Shahapur Taluk of Gulbarga District.
1,11,005 hectares
Completed. The canal is providing irrigation to Shahapur
& Jewargi Taluk of Gulbarga District.
45,015 hectares
Works are Completed. The canal
is providing irrigation to Surpur & Jewargi Taluks of
Gulbarga District and Sindagi & Indi Taluks of Bijapur
District.
1,31,295 hectares
The canal contemplates to provide irrigation
to Shorapur & Jewargi Taluks of Gulbarga District. The
work on entire main canal upto Km. 86.36 and 168 CD
works are completed. Distributary No.1 to 18 are fully
completed. Water has been let out in all the Distributaries.
58,778 hectare
|
|
D. NARAYANPUR RIGHT BANK CANAL -
Main Canal - Length - KM 95.00
Irrigation Area - 84,000 ha.
|
The NRBC canal contemplates irrigation to Lingasugur
& Deodurga Taluks of Raichur District. The entire length
of 95 Kms of main canal including 195 CD works are completed.
All the Distributaries No.1 to 18 are completed. Certain
balance works of Laterals on Distributary No.15, 16
& 18 are in progress. Water is let out in Main Canal
& Distributary 1 to 18.
84,000 hectare.
|
|
E. ALMATTI LEFT BANK CANAL -
Main canal - Length - KM 93.115
Irrigation Area - 20,235 ha.
|
ALBC LI scheme contemplates irrigation to Muddebihal
& Basavana Bagewadi Taluks of Bijapur District. The
headwork is completed. Main Canal works from Km. 0.00
to 67.00 completed. Works from Km. 67.00 to 85.00 except
Km.72 are almost completed. Balance works of Km.72 taken
up separately commenced recently. Distributary No. 1
to 40 are completed. Water let out for irrigation upto
Km.66.00 and Distry.No.1 to 27.
23,480 hectare.
|
|
F. ALMATTI RIGHT BANK CANAL -
Main canal - Length - KM 67.50
Irrigation Area - 9,900 ha.
|
ARBC LI scheme contemplates irrigation to Hungund &
Bagalkot Taluks of Bagalkot District. The headwork and
jackwell structure are completed. The entire length
of main canal from Km. 0.00 to 67.00 completed. Distributaries
1 to 24 completed. Water is let out in main canal &
Distributary No.1 to 24.
9,222 hectare.
|
|
G. MULWAD LIFT IRRIGATION SCHEME
Main Canal - Length - KM 107.40
Irrigation Area - 30,850 ha.
|
Mulwad LI scheme contemplates irrigation to Basavana
Bagewadi Taluk of Bijapur District & Jamakhandi Taluk
of Bagalkot District. Headworks and lead off canal completed.
The entire length of East canal upto 17.40 Kms. completed.
Distributaries, No. 1 to 6 are completed. Extension
of Distributary No.6 work is nearing completion.
West Canal from Km.0.00 to 78.00 is completed. 1 to
43 Distributaries are completed. Water is let out under
East Canal, West Canal and Distributaries thereunder.
22,797 hectare.
|
|
H.RAMPUR LIFT IRRIGATION SCHEME-
Main canal - Length - KM 37.50
Irrigation Area - 20,235 ha.
|
The Rampur LI Scheme contemplates irrigation to Lingasugur
Taluk of Raichur District. First head work at Navali
and second head work near Anahosur completed. 14 Km.
length of lead off channel is completed. The entire
length of East Branch Canal from Km. 0 to 20 and West
Distributary from Km. 0 to 26.14 are completed. The
distributary network including laterals & Field Irrigation
Canals under lead off channel, East Branch Canal and
West distributary are completed & water let out for
irrigation.
19,406 hectare
|
|
I. INDI LIFT IRRIGATION SCHEME -
Main Canal - Length - KM 97.30
Irrigation Area - 41,900 ha.
|
The Indi LI scheme contemplates irrigation to Shorapur
Taluk of Gulbarga District & Sindagi Taluk of Bijapur
District. The Head work and entire main canal work from
Km 0.00 to 97.30 completed including Distributary No.1
to 40 except Distributary No.22. Water has been let
out under completed Distributary network.
41,900 hectare
|
|
2. OTHER PROJECTS UNDER KRISHNA BASIN |
| A.
Ramthal (Marol) Lift Irrigation Scheme |
This
LI Scheme contemplates providing of irrigation facilities
to Hungund Taluk of Bagalkot district for 26,200 hectare
by utilising 5.84 TMC of water. First Headwork on the
backwater of Narayanapur reservoir, near Marol taken up
on turn key basis is completed. Km. 0 to 8 and Km.15.00
to 21.00 of 1st Stage West Main Canal completed. Further
1st stage West Main Canal Km.8.00 to 15.00 is nearing
completion. Tenders awarded recently for 1st stage West
Main Canal Km.21.00 to 45.00 and for Dy.No.12.00 to 18.00.
Work on Distry. No.1 to 6 (except Dy.No.4) are completed.
Distry. No.4 and Dy.No.7 to 11 are in progress. The work
of East canal Km.0.00 to 6.00 is under progress. The Second
head work near Ramwadgi awarded on turn key basis is almost
completed. Work of 110 KV transmission line is completed.
The estimates of canal net work of 2nd stage are under
preparation. |
| B.
Teggi-Siddapur Lift Irrigation Scheme |
This
LI scheme envisages utilization of 1.20 TMC of water (0.90
TMC under scheme 'A') from the backwater of Almatti reservoir
to provide irrigation to 3,000 hectare of Bilagi taluk
of Bagalkot district. Head work with electromechanical
works including balance work of Jackwell awarded on turn
key basis is in progress. Works of Main Canal from Km.0.00
to 12.18 awarded in two packages, are also almost completed.
|
C.
Thimmapur Lift Irrigation Scheme
(ARBC Stage-II)* |
This
LI scheme takes off from Km.4.92 of ARBC. The scheme contemplates
providing irrigation to 20,100 hectare in Hungund taluk
of Bagalkot district. The work of construction of intake
channel, jackwell, pumping machinery, raising main, delivery
chamber etc. awarded on turnkey basis is almost completed.
Works of Main Canal Km.0.00 to 10.00 from Delivery Chamber-1
awarded in two packages nearing completion. Main Canal
from Km.0.00 to 5.00 of DC-2 is in progress. Terminal
bay work for power supply to Head work is completed. |
| D.
Sonna LI Schemes |
This
LI schemes envisage utilization of total 0.233 TMC of
water from the backwater of Almatti reservoir to provide
irrigation to 1,055 hectare lands of Bilagi taluk. The
Scheme is completed & comissioned. Water is let out in
the canal network for irrigation. |
| E.
Rolli-Mannikeri LI Schemes |
This
LI scheme envisage utilization of total 0.73 TMC of water
in the backwater of Almatti reservoir to provide irrigation
to 2,350 hectare lands of Bilagi Taluk. Construction of
jackwell work, providing pumping machinery etc., awarded
on turn key basis is in progress. Works of canal network
awarded recently. |
3.
BARRAGES ON RIVER BHIMA
A. Ghattarga Barrage
B. Kallur 'B' Barrage |
Work completed
Work completed |
| C.
Sonthi Barrage - Lift Irrigation Scheme |
The
scheme contemplates providing irrigation for 16,000 ha
by utilizing 4 TMC of water. Civil work of barrage as
per original scope and the modified scope completed. Erection
of all 37 vertical gates completed. For lifting system,
the excavation for Delivery Chamber and jackwell cum pump
house completed. RCC raft foundation for jackwell completed.
M.S.Pipe rising main is laid for about 3.40 Km. Out of
3000 Mtr length of intake canal, excavation for 1250 mtr
length is tackled. Pumping machineries brought to site.
Construction of Feeder Canal Km. 0.00 to 1.75 is in progress.
Power Transmission Line work is in progress. |
|
D. Yadgir Barrage
E. Joladagi - Gudur Barrage
|
Work completed.
Work completed. |
4.
BARRAGE ON RIVER KRISHNA
Gugal Barrage |
The barrage work is taken up across river Krishna near
Gugal village of Deodurga Taluk. Civil work of Bridge-cum-Barrage
is completed. The work of providing 69 vertical gates
is also almost completed. |
|
5. BARRAGE ON RIVER MANJRA
A. Jirgihal Barrage
B. Manikeshwar Barrage
C. Halhalli Barrage
D. Chandapur Barrage
|
It is envisaged to utilize 4.80 TMC of water by constructing
4 barrages across river Manjra of Godavari basin in Bidar
district. Chandapur Barrage work is completed. Construction
of Jirigihal & Manikeshwar Barrages are in advance stage
of progress. Further Laying of rafts, concreting of Piers,
laying of Deck Slab and Fabrication & erection of embedded
parts / gates for Halhalli Barrages is in progress. |
| Details
on the Investors Grievances received/redressed and pending
for redressal at the period ending 31.12..2011 (details
as submitted by the R&TA & in the Company service provider) |
| Pending
as at 30.09.2011 |
Received
during the quarter between 01.10.2011 & 31.12.2011 |
Total |
Disposed
off during the said period |
Pending
at the end of 31.12.2011 |
|
Nil
|
386
|
386
|
386
|
Nil
|
Note:
1) In general, the progress of work in the project is
satisfactory.
2) Investors' grievances are being attended by the R&TA
service provider M/s. RMV Solutions, 409, 'Joe Nivas',
Chickamaranahalli, New BEL Road, Mathikere, Bangalore-560
054 (Telephone No.080-23600662, Cell Nos. 09343779958)
appointed by the Company and in the in-house of the Company.
3) Investors who have not yet surrendered bond certificates
in respect of Series II (DDB), VIIIA, VIIIB, VIIIC, IXA,
XA, XB, XC, XD, XIB, XIC, XID & XIIA may surrender their
Bond certificates at the earliest to claim refund. |
|
TO WHOMSOEVER IT MAY CONCERN
|
|
To the Series II Deep Discount Bondholders
of Krishna Bhagya Jala Nigam Ltd., Bangalore
Sub: Refund of matured Deep
Discount Bond amount
********
As per the record / data bank maintained by the R&TA-service
provider, M/s. RMV Solutions, Bangalore, there are about
6400 DDB folios / bondholders have not claimed their
matured bond amount. The Series II Deep Discount Bonds
of our Nigam issued during 1996 was due for payment
on maturity on 17.06.2006 ( on completion of 10 years
). As per the terms of the issue, redemption of bond
amount can be made only against surrender of the original
Letter of Allotment (LOA) or the original Bond Certificate
(BC). Almost all the Allottees / Bondholders have surrendered
their original LOAs / BCs and taken the refund of the
bond amount. Now, as per the information provided by
the R&TA service provider, there are about 6400 bondholders
yet to surrender their original LOA / BC ( out of 167657
original Allottees / Bondholders ). We have been publishing
the status of redemption and requesting the unclaimed
bondholders to surrender their original LOA / BC for
redemption purpose, right from the date of maturity,
i.e., 17.06.2006 upto this date. We have also posted
this information on our website www.kbjnl.com. But we
find, still there are about 6400 deep discount bondholders
yet to respond in surrendering the original LOA / BC
for redemption purpose.
As per the Company Law provisions [ Section 205(C)
], the unclaimed bond amount will have to be deposited
in Central Govt. account called " Investor Education
Protection Fund" (IEPF) account on completion of 7 years
from the date of payment on maturity, 17.06.2006. Accordingly
our Company is required to deposit the unclaimed and
left over bond amount by 16.06.2013 in IEPF account.
Once the amount is deposited in IEPF Account, it will
go to Central Govt. and nobody can claim for refund
of bond amount and it will be a loss to the bondholders.
Hence the concerned unclaimed Deep Discount Bondholders
may please surrender their original Letter of Allotment
/ Bond Certificate at the earliest to our Company or
to the R&TA service lending agency, M/s. RMV Solutions,
409, 'Joe Nivas', Chickamaranahalli, New BEL Road, Mathikere,
Bangalore-560 054 ( Telephone No.080-23600662,
Cell Nos. 09343779958 of Mr. Ramesh Manuel and 0991653475
of Ms.Yeshaswini) at the earliest for refund of
the matured bond amount. If there is any grievance,
like change of address, Transmission of bonds, issue
of duplicate LOA/BC etc., the same may also be addressed
for immediate redressal and take it for redemption.
For kind information and for urgent needful action
at your end.
|
|
Date : 27.01.2012....................................................
Place : Bangalore.. .......................................
MANAGING DIRECTOR
|