Progress Report of the Project
PROGRESS REPORT OF UPPER KRISHNA PROJECT AS AT 31.12.2017
UNITS / PROGRAMMED |
PROGRESS AS AT 31.12.2017 * |
Irrigation Area – 6,22,023 Hectare |
Completed including balance work at Km.72.00 of ALBC.
6,18,932 Hectares |
Irrigation Area – 5,30,000 Hectare |
Implementation of project sub-components namely: (1) Mulwad LIS Stage – III, (2) Chimmalagi LIS, (3) Indi LIS (Gutti Basavanna) --Extension, (4) Mallabad LIS, (5) Rampur LIS --Extension, (6) NRBC Extension, (7) Koppal LIS, (8) Herkal LIS and (9) Bhima Flank to provide Irrigation for envisaged 5.3 lakhs Hectare area in Kalaburgi, Yadgiri, Vijayapur, Bagalkot, Raichur, Koppal and Gadag Districts in Northern Karnataka.
Project works are in progress alongwith Land Acquisition (Submergence, R.C. Centers and Canal Network), Rehabilitation & Resettlement and BTDA Works |
3. OTHER PROJECTS UNDER KRISHNA BASIN |
|
A. Ramthal (Marol) Lift Irrigation Scheme
Irrigation Area – 36,000 Hectare |
This LI Scheme contemplates providing of irrigation to Hungund Taluk of Bagalkot district for 26,200 hectare by utilising 5.84 TMC of water. 1st Headwork in the backwater of Narayanapur reservoir, near Marol is completed.
1st Stage West Main Canal -- From Km. 0.00 to 62.00 including Distry.No.1 to 25 completed.
1st Stage East Main Canal -- From Km.0.00 to 52.00 including Distry. No.1 to 20 are completed & water let out for irrigation.
2nd Stage: Head work near Ramwadagi is completed.
Government vide G.O. dated 16.06.2012, has accorded Administrative approval for implementing Gravity based Micro-irrigation (Drip irrigation) under 2nd Stage of Ramthal LIS for 24,000 Ha on pilot basis, at an estimated cost of Rs.786.11 Crores (2011-12 Price Level) including 3 years O & M.
Drip Irrigation system works under 2nd stage of Ramthal (Marol) LIS for 24,000 Ha. of Command area awarded on turn key basis in two packages are completed and irrigation is commenced from kharif 2017 season.
34,493 Ha. |
B. Teggi-Siddapur Lift Irrigation Scheme
Irrigation Area – 3,000 Hectare |
This LI scheme envisages utilization of 0.90 TMC of water from the backwater of Almatti reservoir to provide irrigation to 3,000 Hectare of Bilagi taluk of Bagalkot district.
The scheme is completed and commissioned.
3,000 Ha. |
C. Thimmapur Lift Irrigation Scheme
Irrigation Area: 20,100 Hectare |
This LI scheme takes off from Km.5.40 of Almatti Right Bank Canal. The scheme contemplates providing irrigation to 20,100 hectare in Hungund taluk of Bagalkot district. The Head work awarded on turnkey basis is completed & commissioned.
DC-1:
1) Main Canal Km.0.00 to 43.00 & Distry. No.1 to 23 under DC-1 completed.
2) Main Canal Km.43.00 to 53.00 not tackled due to obstruction by Benakatti Villagers (Grama Sabha resolution passed). Balance work of Main Canal Km.46.70 to 53.00 is nearing completion.
DC-2:
1) Main Canal Km.0.00 to 28.00 & Dy.No.1 to 10 completed.
2) Further due to obstruction by Benakatti villagers (Grama Sabha resolution passed). Main Canal construction curtailed at Km. 28.00. For creating balance available potential under DC-2, Dy.No.11 is taken up & nearing completion.
17,482 Hectares. |
D. Sonna LI Schemes
Irrigation Area: 1,050 Hectare |
This LI schemes envisage utilisation of total 0.27 TMC of water from the backwater of Almatti reservoir to provide irrigation to 1,055 hectare of command in Bilagi taluk.
The Scheme is completed & commissioned.
950 Hectares. |
E. Rolli-Mannikeri LI Schemes
Irrigation Area: 2,450 Hectare |
This LI scheme envisages utilisation of total 0.73 TMC of water in the backwater of Almatti reservoir to provide irrigation to 2,350 hectare of command in Bilagi Taluk.
Head work & canal network under DC-1 & 3 of the scheme are completed and balance canal network under DC-2 is almost completed. Water let out for Irrigation in the completed Canal Network
2,350 Hectares. |
4. BARRAGES ON RIVER BHIMA
A. (i) Ghattarga, (ii) Kallur ‘B’ Barrage, (iii) Yadgir & (iv) Joladagi – Gudur Barrages |
These Barrages are completed and water stored to be utilized by farmers for irrigation through their own pump sets/ lift. |
B. Sonthi Barrage – Lift Irrigation Scheme
Irrigation Area: 16,100 Hectare |
The scheme contemplates providing irrigation for 16,000 ha by utilising 4 TMC of water. Civil work of barrage & Erection of all 37 vertical gates completed and water stored at Barrage.
For lifting system, Head Work on turnkey basis (balance work) is almost completed. Trial run conducted.
Construction of Feeder Canal work is completed. Works of Sonthi LIS Main Canal Km 0.00 to 18.00 (including Aqueduct), Sonthi Branch Canal Km 0.00 to 20.02, Distry. No.1 Km 0.00 to 15.00 & Yargol Minor Canal works are in advance stage of progress. Furtherance for modified alignment for construction of aqueduct reach from Km 24 to Km 33 Km of Sonthi Main canals estimate is finalized and tender being invited.
8,194 Ha. |
5. BARRAGE ON RIVER MANJRA -
A. Jirgihal Barrage
B. Manikeshwar Barrage
C. Chandapur Barrage
D. Halhalli Barrage |
It is envisaged to utilise 4.80 TMC of water by constructing 4 series of barrages across River Manjra of Godavari basin in Bidar district.
All the four Bridge-cum-Barrages, viz., Jirgihal, Manikeshwar, Halhalli and Chandapur Bridge cum Barrage works are completed.
The water stored at Barrages to be utilized by farmers through their pump sets / lifts. For the works of providing low level friction dampers tenders in two packages are in process. |
|
Gugal Bridge-cum-Barrage with across river Krishna in Deodurga Tq. of Raichur Dist. Is completed. Water stored at barrage being utilized by farmers through own pumpsets / lifts. |
7. NRBC Distry.No.9A
A. Construction of NRBC Dy, 9A :
|
Contemplates providing irrigation for 15,250 Ha. in Deodurga & Manvi Taluks of Raichur District.
Package works are completed and irrigation facility provided. |
B. Construction of Arkera Branch Canal :
Km.0.00 to 22.87 (Package – I, II & III) |
The works under 3 packages (including Aqueduct) are completed and irrigation facility provided.
|
C. Construction of Wadavatti Branch Canal:
i) Package-I (from Km.0.00 to 10.00)
ii) Package-II, III & IV (Km.10.00 to 28.37)
Irrigation Area: 15,250 Hectare |
Package work almost completed.
Package works are under progress.
10,298 Ha. |
*Note: The above does not include, projects already completed.
Details on the Investors Grievances received/redressed and pending for redressal for the period ending 31.12.2017 (details as submitted by the R&TA & in the Company)
|
||||
Pending as at 30.09.2017 |
Received during the quarter between 01.10.2017 & 31.12.2017
|
Total |
Disposed off during the said period |
Pending at the end of 31.12.2017 |
Nil |
Nil |
Nil |
Nil |
Nil |
Note: 1) In general, the progress of work in the project is satisfactory. 2) Investors’ grievances are being attended by the Registrar and Transfer Agents appointed by the company and in-house by Company.
Date : 20 .01.2018
Place : Bengaluru MANAGING DIRECTOR |