PROGRESS REPORT OF UPPER KRISHNA
PROJECT AS AT 30.09.2008
(In accordance with the Listing Agreement entered into
with the National Stock Exchange)
|
|
UNITS / PROGRAMMED
|
PROGRESS AS AT 30.09.2008
|
|
A. NARAYANPUR DAM AND ALLIED WORKS
B. ALMATTI DAM AND ALLIED - WORKS
i) Left Bank Earth and Masonry Dam-
EL 528.800 m
ii) Spill Way - EL 509.016 m
iii) Right Bank Masonry Dam-Power Dam -
EL 528.760 m
Non-overflow Section - EL.528.760m
iv) Providing Gates - 26 Nos.
|
Completed.
Completed.
The works pertaining to Dam including Gates have been
completed. Water is stored upto FRL.519.60 m and being
utilised.
|
|
C. NARAYANPUR LEFT BANK CANAL
i) Main Canal - Length - KM 78
Irrigation Area - 47,233 ha.
ii) Shahpur Branch Canal -
Main Canal - Length - KM 76
Irrigation Area - 1,22,120 ha.
iii) Mudbal Branch Canal -
Main Canal - Length - KM 50.80
Irrigation Area - 51,000 ha.
iv) Indi Branch Canal -
Main Canal - Length - KM 175
Irrigation Area - 1,31,260 ha.
v) Jewargi Branch Canal -
Main Canal - Length - KM 86.36
Irrigation Area - 57,100 ha
|
Completed. The canal is providing irrigation to Shorapur
Taluk of Gulbarga District.
53,590 hectares
Completed. The canal is providing irrigation to Shorapur
& Shahapur Taluk of Gulbarga District
1,10,928 hectares
Completed. The canal is providing irrigation to Shahapur
& Jewargi Taluk of Gulbarga District.
45,015 hectares
Works are Completed. The canal is providing irrigation
to Surpur & Jewargi Taluks of Gulbarga District and
Sindagi & Indi Taluks of Bijapur District.
1,31,295 hectares
The canal contemplates to provide irrigation to Shahapur
& Jewargi Taluks of Gulbarga District. The work on entire
main canal upto Km. 86.36 and 168 CD works are completed.
Distributary No.1 to 18 are fully completed. Water has
been let out in all the Distributaries.
57,736 hectare
|
D. NARAYANPUR RIGHT
BANK CANAL -
Main Canal - Length - KM 95.00
Irrigation Area - 84,000 ha. |
The NRBC canal contemplates irrigation to Lingasugur
& Deodurga Taluks of Raichur District. The entire length
of 95 Kms of main canal including 195 CD works are completed.
All the Distributaries No.1 to 18 are completed. Certain
balance works of Branch Distributary, Laterals on Distributary
No.15, 16 & 18 are in progress. Water is let out in
main canal & Distributary 1 to 18.
84,000 hectare.
|
E. ALMATTI LEFT BANK
CANAL -
Main canal - Length - KM 93.115
Irrigation Area - 20,235 ha. |
ALBC LI scheme contemplates irrigation to Muddebihal
& Basavana Bagewadi Taluks of Bijapur District. The
headwork is completed. Main Canal works from Km. 0.00
to 67.00 completed. Works from Km. 67.00 to 85.00 except
Km.72 are in almost completed. Among 43 Distributaries,
Distributary No. 1 to 28 are completed and Distributary
29 to 40, the works are nearing completion except Distributary
No.29.
21,554 hectare.
|
|
F. ALMATTI RIGHT BANK CANAL -
Main canal - Length - KM 67.50
Irrigation Area - 9,900 ha.
|
ARBC LI scheme contemplates irrigation to Hungund &
Bagalkot Taluks of Bagalkot District. The headwork and
jackwell structure are completed. The entire length
of main canal from Km. 0.00 to 67.00 completed. Distributaries
1 to 24 completed. Water is let out in main canal &
Distributary No.1 to 24.
9,062 hectare.
|
|
G. MULWAD LIFT IRRIGATION SCHEME -
Main Canal - Length - KM 107.40
Irrigation Area - 30,850 ha.
|
Mulwad LI scheme contemplates irrigation to Basavana
Bagewadi Taluk of Bijapur District & Jamakhandi Taluk
of Bagalkot District. Headworks and lead off canal completed.
The entire length of East canal upto 17.4 0 Kms. completed.
Out of 6 Distributaries, No. 1 to 5 are completed and
work in Distributary No. 6 is nearing completion.
West Canal from Km.0.00 to 78.00 is completed. Among
43 Distributaries, 1 to 29 are completed and Distributary
No. 30 to 43 are almost completed. Water is let out
under East Canal, West Canal and Distributaries thereunder.
20,970 hectare.
|
|
H. RAMPUR LIFT IRRIGATION SCHEME-
Main canal - Length - KM 37.50
Irrigation Area - 20,235 ha.
|
The Rampur LI Scheme contemplates irrigation to Lingasugur
Taluk of Raichur District. First head work at Navali
and second head work near Anahosur completed. 14 Km.
length of lead off channel is completed. The entire
length of East Branch Canal from Km. 0 to 20 and West
Distributary from Km. 0 to 26.14 are completed. The
distributary network including Field Irrigation Canals
under lead off channel are completed. Construction of
laterals and Field Irrigation Canals under East Branch
Canal and West distributary are almost completed. Water
has been let out under lead off canal, East Branch Canal
& West Distributary.
19,331 hectare
|
|
I. INDI LIFT IRRIGATION SCHEME -
Main Canal - Length - KM 97.30
Irrigation Area - 41,900 ha.
|
The Indi LI scheme contemplates irrigation to Shorapur
Taluk of Gulbarga District & Sindagi Taluk of Bijapur
District. The construction of head regulator and intake
canal are completed. The jackwell and pump house are
completed. The works of transmission line, erection
of 6 pumps and 6 motors completed. Entire main canal
work from Km 0.00 to 97.30 completed. Distributary No.1
to 31 are completed except Distributary No.22. Works
on Distributary No.32 to 40 are almost completed. For
balance works on Distributary No.22 package estimate
and Draft Tender Papers are prepared and tenders to
be invited. Water has been let out under completed Distributary
network.
41,813 hectare
|
|
2. OTHER PROJECTS UNDER KRISHNA BASIN
|
|
|
A. Ramthal (Marol) Lift Irrigation Scheme
B. Teggi-Siddapur Lift Irrigation Scheme
C.Thimmapur Lift Irrigation Scheme
(ARBC Stage-II)
D. Sonna LI Schemes
E. Rolli - Mannikeri LI Schemes
|
This LI Scheme contemplates providing of irrigation
facilities to Hungund Taluk of Bagalkot district for
26,200 hectare by utilising 5.84 TMC of water. The location
of the first jackwell is on the backwater of Narayanapur
reservoir, near Marol village. The work for construction
of intake channel, jackwell, pumping machinery, raising
main, delivery chamber, etc. for first Jackwell awarded
on turnkey basis is almost completed. Km. 0 to 8 of
West Main Canal work is under progress. The Second head
work including construction of jackwell, providing pumping
machinery, raising main, etc. awarded on turn key basis,
is in progress. The work of 110 KV transmission line
is nearing completion.
This LI scheme envisages utilisation of 1.20 TMC of
water (0.90 TMC under scheme 'A') from the backwater
of Almatti reservoir to provide irrigation to 3,000
hectare of Bilagi taluk of Bagalkot district. The construction
of intake channel and jackwell work is in progress.
Tenders for main canal work is to be invited, as the
tender process (2nd call) was cancelled. Estimates &
DTP for electromechanical works & balance work of Jackwell
are under finalisation & tenders on turn key basis to
be invited. .
This LI scheme takes off from Km 4.92 of ARBC. The
scheme contemplates providing irrigation to 20,100 hectare
in Hungund taluk of Bagalkot district. The work of construction
of intake channel, jackwell, pumping machinery, raising
main, delivery chamber etc. awarded on turnkey basis
is under progress. The Survey investigation of canal
network is under progress. Estimates for Km. 1 to 10
of delivery chamber -2 are under preparation.
This LI schemes envisage utilisation of total 0.233
TMC of water from the backwater of Almatti reservoir
to provide irrigation to 1,055 hectare lands of Bilagi
taluk. The construction of jackwell intake channel provide
pumping machinery etc., awarded on turnkey basis is
under progress
These schemes envisage utilization of total 0.51 TMC
of water in the backwater of Almatti reservoir to provide
irrigation to 2,350 hectare lands of Bilagi Taluk. The
construction of jackwell work, providing pumping machinery
etc., awarded on turn key basis is rescinded as the
firm has not commenced the work & tenders are to be
re-invited.
|
| 3.
BARRAGES ON RIVER BHIMA. |
|
|
A. Ghattarga Barrage
B. Kallur 'B' Barrage
C. Sonthi Barrage - Lift Irrigation Scheme
D. Yadgir Barrage
E. Joladagi - Gudur Barrage
|
Work completed.
Work completed.
Government has accorded administrative approval to
the modified Sonthi Barrage/ LI Scheme at a cost of
Rs.188.00 crores. The scheme contemplates providing
irrigation for 17,000 ha by utilizing 4 TMC of water.
Civil work of barrage as per original scope is completed
and the modified scope of civil work is nearing completion.
Out of total 37 vertical gates, fabrication of 28 gates
are completed and fabrication for remaining gates are
in progress. For lifting system the excavation for delivery
chamber and jackwell cum pump house almost completed.
Fabrication of M.S.Pipe rising main is completed for
about 3.10 Km. Out of 3000 Mtr length of intake canal,
excavation for 1200 mtr length is completed.
Work completed.
Work completed.
|
|
4. BARRAGE ON RIVER KRISHNA
Gugal Barrage
|
The
barrage work is taken up across river Krishna near Gugal
village of Deodurga Taluk. Main barrage work is completed.
For the work of providing vertical gates awarded on turn
key, fabrication of gate works is in progress. |
|
5. BARRAGE ON RIVER MANJRA
A. Jirgihal Barrage
B. Manikeshwar Barrage
C. Halhalli Barrage
D. Chandapur Barrage
|
It is envisaged to utilize 4.80 TMC of water by constructing
4 barrages across river Manjra of Godavari basin in
Bidar district. Excavation for foundation completed.
Laying of rafts and concreting of Piers in progress.
As regards providing automatic lifting gate works of
4 barrages, in respect of Manikeshwar Barrage 8 gates
are erected. Fabrication of embedded parts and gates
of other barrages are in progress.
|
|
Details on the Investors Grievances received/redressed
and pending for redressal at the perod ending 30.09..2008
(details as submitted by the R&TAs & in the Company)
| Pending as at 30.06.2008 |
Received
during the quarter between 1.7.2008 & 30.9.2008 |
Total |
Disposed off during
the said period |
Pending at the end
of 30.09.2008 |
|
45
|
1282
|
1327
|
1280
|
47
|
Note:
1) In general, the progress of work in the project
is satisfactory.
2)The Finance, Remuneration and Bondholders / Investors
Transfer Committee / Compliance Officer is reviewing
the investors' grievances as attended by the R&TAs and
also as attended by the Company. *The pending cases
as at 30.09.2008 have been attended as ongoing works
by all the R&TAs and in the Company.
3) Investors who have not yet surrendered bond certificates
in respect of Series II ( DDB), IV, V, VIA & VIB, VIIA
& VIIB, VIIIB, VIIIC, IXA, I XB, XA,XB,XC,XD,XIB,XIC,XID
& XIIA may surrender their Bond certificates at
the earliest to claim refund.
Date:24.10.2008.